Contract # D258528

Contract Name:

Rehabilitation of Route 22 Bridge over Rye Lake Outlet In the Town of North Castle

 

 

Agency:New York State Department of Transporation
Engineer:Boswell Engineering
Contract Amount:$14,456,559
Contract Completion:2005
Percent Completed By Ecco:85%
Scope of Work:
This project consisted of the complete removal and replacement of an eight hundred foot long bridge over the Kensico Reservoir for the New York City Department of Environmental Protections Aqueduct System. The superstructure consisted of floor beams and deck to be replaced with floor beam and bearings and exodermic deck system. Additional work consisted of substructure concrete repair and minor drainage improvements.
---